15 May 2016

Washroom Renovation Update #6

Plumbing to the Clubhouse (including hot water) is complete as of 13 May allowing use of kitchen and laundry room.  Neptune’s Bar still needs some significant cleaning which will follow in the next week. A replacement of the lighting and cScreen Shot 2016-05-15 at 9.47.26 AMeiling in the main (north) entrance has been added in order to move this design into the 21st century, to include painting.  Therefore, this area remains a CONSTRUCTION ZONE for the most part.

The projected target for functional washrooms is 19 May. Showers are in place and toilets being installed. Sinks and countertops are scheduled for next week. However, there have been some delays in delivery dates of toilet partitions and shower stall doors and theScreen Shot 2016-05-15 at 9.46.32 AM fan systems in main washrooms. The prime Contractor is expediting where possible and has proposed temporary toilet partitions and shower curtains as an interim measure. An occupancy permit from the City of Kingston is still a requirement and there are never any guarantees.

Please also note that as that the “executive” washrooms are under contract to 20 May with an extension to 1 June at no cost unless required and rented elsewhere.

Pierre de Gagné