07 May 2016

Washroom Renovation Update #5

Things are moving well on the renovation front. Please note that this weekend (May 6,7 and 8) will see some overtime work as it is planned that tiling will commence on the floor and walls.

PLEASE RESPECT THAT THIS AREA REMAINS A CONSTRUCTION ZONE.

All inspections to date have “passed”. City of Kingston approved plumbing and this has allowed close in of walls and chase areas. JLR Architects has done three site visits with accompanying Site Observation Reports endorsing progress to date. Future inspections are planned.

WATER STATUS – Potable well water has been provided to the East and West Harbours only at this time. The

Clubhouse will not have water until next week (week of 9 May) but this will include hot water post installation of electric water heaters. Showers will follow in a timely fashion. Barring any unforeseen circumstances, occupancy is anticipated week of 16 May with intent to commission the Universal Washroom earlier pending City of Kingston approvals.

It is noted RD Steele Construction Limited of Brockville has been very proactive in managing this project and coordinating the various sub contractors. A BRAVO ZULU for their efforts and excellent progress to date.

Pierre de Gagné