09 Sep 2016

Washroom Renovation Update #9

While you have been enjoying the best summer ever ‐ please be advised that there remain deficiencies to be resolved.

Major Issues:
Deficient tiling is being redone. RD Steele has hired a new subcontractor to replace the tile in the washrooms.

The universal washroom will be closed for the week of September 12 for repairs of the
existing tile to the satisfaction of TYC.

A new tile (4″ by 12″) will be installed in the Men’s and Women’s washrooms. This work will commence post early launch (October 3) and take approximately three weeks per washroom.

Please respect that this will be a work site for the above periods and washrooms will be closed and those normally using the closed washroom will be using the universal
washroom.
Pierre de Gagné